Project Timelines
-
2023 & 2024 Bonds
Bond projects are chosen by evaluation using the Facilities Assessment document. Age is one of the main criteria, but other considerations include relevant work order history and evaluation by the facilities team. The projects are then prioritized for start and completion based on these evaluation scores.
All timelines are subject to change due to various factors such as material availability, vendor timelines, efforts to avoid campus disruption, etc.
-
Summer 2024 (Current Projects)
Marquee Replacements:
- Garden Ridge Elementary
- Old Settlers Elementary
- Lamar Middle School
- Griffin Middle School (logo replacement only)
Additions & Renovations:
- TECC-E
New Track & Field Lighting
- All five high schools
Interior Bleacher Replacements:
- Arbor Creek Middle School
Multi-Purpose Facility & Concession:
- The Colony High School
Casework Replacements (select areas):
- Arbor Creek Middle School
- Lamar Middle School
Replacement or enhancement of elementary playgrounds with new accessibility style:
- Forest Vista (complete)
- Indian Creek (complete)
- Lakeland (complete)
- McAuliffe (complete)
- Morningside (complete)
- Polser (complete)
- Southridge (complete)
Marquee Replacements:
- Garden Ridge Elementary
- Old Settlers Elementary
- Lamar Middle School
Emergency Responder Radio System:
- Arbor Creek MS
- Assesment Center & Textbook Warehouse
- BB Owen ES
- Briarhill MS
- Camey ES
- Castle Hills ES
- Creek Valley MS
- Degan ES
- DeLay MS
- Donald ES
- Downing MS
- Flower Mound ES
- Forest Vista ES
- Forestwood MS
- Garden Ridge ES
- Griffin MS
- Hebron Valley ES
- Heritage ES
- Hicks ES
- Highland Village ES
- Homestead ES
- Huffines MS
- Independence Elementary
- Indian Creek Elementary
- Lakeland ES
- Lamar MS
- Liberty ES
- Lewisville ES
- Lewisville Learning Center
- LISD Administrative Center
- LISD Outdoor Learning Area
- Marcus HS- Softball Field
- Marcus Marauder Baseball Field
- McAuliffe ES
- McKamy MS
- Mill Street ES
- Morningside ES
- Peters Colony ES
- Polser ES
- Prarie Trail ES
- Rockbrook ES
- TECC- E
- Timber Creek ES
- Valley Ridge ES
- Vickery ES
- Wellington ES
Furniture Replacements:
- Arbor Creek Middle School (complete)
- Briarhill Middle School (complete)
- Creekside Elementary (cafe table only) (complete)
- DeLay Middle School (complete)
- Forestwood Middle School (complete)
- Garden Ridge Elementary (complete)
- Huffines Middle School (complete)
- Independence Elementary (complete)
- Killian Middle School (complete)
- Lewisville Elementary (complete)
- Lakeland Elementary (complete)
- Lamar Middle School (complete)
- McAuliffe Elementary (complete)
- McKamy Middle School (complete)
- Morningside Elementary (complete)
- Peters Colony Elementary (complete)
Installation of elementary playground shade structures:
- Bridlewood (PreK) (complete)
- Donald (PreK) (complete)
- Ethridge (PreK) (complete)
- Forest Vista (PreK) (complete)
- Garden Ridge (Main) (complete)
- Hebron Valley (PreK) (complete)
- Heritage (PreK) (complete)
- Indian Creek (Main & PreK) (complete)
- Lakeland (Main) (complete)
- Lewisville ES (Main) (complete)
- McAuliffe (Main) (complete)
- Morningside (Main) (complete)
- Parkway (PreK) (complete)
- Polser (Main & PreK) (complete)
- Southridge (Main & PreK) (complete)
New Track & Field Lighting
- All five high schools
Flooring Replacements (select areas):
- Griffin Middle School (complete)
- Independence Elementary (complete)
- Killian Middle School (complete)
- Lakeland Elementary (complete)
- Lamar Middle School (complete)
Casework Replacements (select areas):
- Arbor Creek Middle School
- Garden Ridge Elementary (complete)
- Lamar Middle School
- Morningside Elementary (complete)
Technology:
- PK-3 Grade iPad Prep and Deployment for 24-25 SY
- 7-9, and 11-12 grade iPad Prep for 24-25 SY
- Prep Program Specific Technology for 24-25 deployment
- Update Campus Paging Systems at:
- Lewisville High School
- Rockbrook Elementary
- Independence Elementary
- McAuliffe Elementary
- Lillie Jackson Eearly Childhood Center
- UPS replacement in LISD Administrative Center Data Center
- Security Camera Storage Replacement
- Enterprise Backup System Replacement
- Enterprise Resource Planning (ERP) Software Replacement Implementation
-
Summer 2025
- Year 1 Casework Replacements (Arbor Creek, Garden Ridge, Lamar, Morningside)
- High School Furniture Replacements (LHS and HHS 9th Grade)
- Fine Arts- Lewisville HS Scene Shop Addition and Band Lot Renovations
- Fine Arts- LHS Harmon Black Box Theatre Conversion
- Castle Hills ES 20 Year Life Cycle Maintenance and Repair (Playground)
- Central ES Partial 20 Year Life Cycle Maintenance and Repair (Roof, Playground and Shade)
- Degan ES Partial 20 Year Life Cycle Maintenance and Repair (Roof, Playground and Shade)
- Liberty ES 20 Year Life Cycle Maintenance and Repair (Playground)
- Creek Valley Middle School 20 Year Life Cycle Maintenance and Repair
- Downing Middle School 20 Year Life Cycle Maintenance and Repair (Elevator)
- Durham Middle School 20 Year Life Cycle Maintenance and Repair (Elevator)
- Flower Mound HS Phase-2 20 Year Life Cycle Maintenance and Repair
- Hebron HS Phase-2 20 Year Life Cycle Maintenance and Repair
- Lewisville Learning Center 20 Year Life Cycle Maintenance and Repair
- Marcus High School Partial 20 Year Life Cycle Maintenance and Repair (w/elevator, gym floor, bleachers, paving)
- The Colony High School Partial 20 Year Life Cycle Maintenance and Repair (Flooring, bleachers)
- New Transportation Center
- Year 1 Roofing (Facility Services w/HVAC, Welcome Center, Lamar, Old Settlers)
- Year 1 Electrical Upgrades (Arbor Creek, Garden Ridge, Morningside)
- Year 1 Elevator Renovations (Arbor Creek, Huffines)
- Year 1 Fire Alarm Upgrades (Lamar, LHS Harmon)
- Year 1 Paving Replacement (Assessment Center and Creekside ES)
- Doors and Hardware Replacements (Forestwood, Garden Ridge, Lamar, McAuliffe, Morningside)
- Lewisville High School Renovations (1999 Restrooms, Roof, Elev, Fire Alarm, Weight Room HVAC)
- LISDAC Security Enhancements including doors and hardware, District Wide Door Hardening (Classroom and Secondary Entrances) and High School Secondary Security Vestibules
- District Wide Generators and Radio System UPS
- District Wide Security Upgrades (Keyless Entry, Burglar Alarm, Radio System, Security Camera upgrade, and HVAC override)
- Traffic Signal at Hebron High School
- Aquatic Center East 20-Year Life Cycle Maintenance and Repair
- All High Schools - Turf Baseball Fields
- All High Schools - Turf Softball Fields (Except TCHS)
- All High Schools - Turf One Practice Field per Campus
- All High Schools - Baseball and Softball Field Lighting Upgrades (Except TCHS SB)
- Middle School Game Field Turf (Griffin, Harmon, Shadow Ridge)
- Year 1 Track Replacements (Downing MS, Harmon, Shadow Ridge MS)
- Year 1 Tennis Court Resurfacing (Flower Mound HS, Marcus HS, The Colony HS)
- Hebron High School 2003 Field House 20-Year Life Cycle Maintenance and Repair
- Hebron High School Baseball and Softball Field Renovations
- All High Schools - Replace Stadium Lighting with LED (Football Stadiums Only)
- Year 1 Track Replacements (Flower Mound HS, Hebron HS, Lewisville HS, The Colony HS)
- Year 1 Football Stadium Scoreboards (Flower Mound HS, Hebron HS, Lewisville HS, The Colony HS)
- Flower Mound Stadium 20-Year Life Cycle Maintenance and Repair
- Hebron High School Stadium 20-Year Life Cycle Maintenance and Repair
-
Summer 2026
- Flower Mound HS Phase-2 20 Year Life Cycle Maintenance and Repair
- Hebron HS Phase-2 20 Year Life Cycle Maintenance and Repair
- Castle Hills ES 20 Year Life Cycle Maintenance and Repair (Playground)
- Central ES Partial 20 Year Life Cycle Maintenance and Repair (Roof, Playground and Shade)
- Degan ES Partial 20 Year Life Cycle Maintenance and Repair (Roof, Playground and Shade)
- Liberty ES 20 Year Life Cycle Maintenance and Repair (Playground)
- Creek Valley Middle School 20 Year Life Cycle Maintenance and Repair
- Downing Middle School 20 Year Life Cycle Maintenance and Repair (Elevator)
- Durham Middle School 20 Year Life Cycle Maintenance and Repair (Elevator)
- Lewisville Learning Center 20 Year Life Cycle Maintenance and Repair
- Marcus High School Partial 20 Year Life Cycle Maintenance and Repair (w/elevator, gym floor, bleachers, paving)
- The Colony High School Partial 20 Year Life Cycle Maintenance and Repair (Flooring, bleachers)
- New Transportation Center
- Year 1 Electrical Upgrades (Arbor Creek, Garden Ridge, Morningside)
- Year 1 Fire Alarm Upgrades (Lamar, LHS Harmon)
- District Wide Generators and Radio System UPS
- District Wide Security Upgrades (Keyless Entry, Burglar Alarm, Radio System, Security Camera upgrade, and HVAC override)
- McAuliffe Renovations (Casework, Flooring, Marquee, Stage Curtains, Exterior Lighting)
- Coyote Ridge ES 20 Year Life Cycle Maintenance and Repair (Playground and Shade)
- Flower Mound ES 20 Year Life Cycle Maintenance and Repair (Marquee, Playground and Shade)
- Hicks ES 20 Year Life Cycle Maintenance and Repair (Playground and Shade)
- Rockbrook ES 20 Year Life Cycle Maintenance and Repair (Playground and Shade)
- Vickery ES 20 Year Life Cycle Maintenance and Repair (Playground and Shade)
- LHS Killough 20 Year Life Cycle Maintenance and Repair - Main Campus
- Briarhill MS Renovations (Boiler, Electrical, Elevator, Interior Bleachers, Marquee, Fire Alarm)
- McKamy MS Renovations (Electrical, Elevator, Flooring, Interior Bleachers, Marquee)
- Forestwood MS Renovations (Elevator, Flooring, Interior Bleachers, Marquee, Fire Alarm)
- Year 2 Flooring (Assessment/Textbook, HHS 9, LHS, Peters Colony)
- Year 2 Playground (Creekside) and Shade Structures (6 Campuses)
- Timbercreek ES Marquee
- DeLay Parking and Sidewalks
- Year 2 Roofing (Creekside ES, Timbercreek ES)
- DeLay Fire Alarm
- Aquatic Center East 20-Year Life Cycle Maintenance and Repair
- Aquatic Center West - Video Scoreboard, Small Pool Liner, Bulkhead Surfacing
- Flower Mound HS Baseball and Softball Locker Room Addition
- Forestwood Middle School Track Replacement
- Lewisville HS Baseball Concessions Replacement and Restroom Renovations
- Lewisville HS Boys Track Locker Room 20-Year Life Cycle Maintenance and Repair
- Lewisville HS Indoor Athletic Center Upgrades
- Marcus HS Baseball Locker Room Addition
- The Colony HS Indoor Athletic Center Upgrades
-
Summer 2027
- Marcus High School Partial 20 Year Life Cycle Maintenance and Repair (w/elevator, gym floor, bleachers, paving)
- The Colony High School Partial 20 Year Life Cycle Maintenance and Repair (Flooring, bleachers)
- Coyote Ridge ES 20 Year Life Cycle Maintenance and Repair (Playground and Shade)
- Flower Mound ES 20 Year Life Cycle Maintenance and Repair (Marquee, Playground and Shade)
- Hicks ES 20 Year Life Cycle Maintenance and Repair (Playground and Shade)
- Rockbrook ES 20 Year Life Cycle Maintenance and Repair (Playground and Shade)
- Vickery ES 20 Year Life Cycle Maintenance and Repair (Playground and Shade)
- LHS Killough 20 Year Life Cycle Maintenance and Repair - Main Campus
- DeLay Fire Alarm
- LISDAC Renovations (Casework, Flooring, HVAC & Controls, Restrooms)
- Indian Creek ES 20 Year Life Cycle Maintenance and Repair
- Lillie Jackson ECC 20 Year Life Cycle Maintenance and Repair (Playground and Shade)
- Shadow Ridge MS 20 Year Life Cycle Maintenance and Repair
- Owen ES Renovations (Roof, Stage Curtain, Flooring, Playground and shade, furniture, casework, electrical, and fire alarm)
- Year 3 Flooring (DeLay, FMHS, HHS, Lewisville ES, MHS, TECC-E)
- Year 3 Marquees (Bridlewood, Killian, Prairie Trail, Wellington)
- Year 3 Parking Lots and Sidewalks (Degan and Highland Village ES)
- Year 3 Playground (Highland Village, Student Success Center) and Shade Structure (Student Success Center)
- Year 3 Fire Alarm Upgrades (Griffin and TCHS Bus Barn)
- Year 3 Exterior Lighting (15 Campuses)
- LHS Killough Athletics 20-Year Life Cycle Maintenance and Repair
- LHS Killough Track Replacement
-
Summer 2028
- LISDAC Renovations (Casework, Flooring, HVAC & Controls, Restrooms)
- Indian Creek ES 20 Year Life Cycle Maintenance and Repair
- Lillie Jackson ECC 20 Year Life Cycle Maintenance and Repair (Playground and Shade)
- Shadow Ridge MS 20 Year Life Cycle Maintenance and Repair
- Year 3 Fire Alarm Upgrades (Griffin and TCHS Bus Barn)
- Year 3 Exterior Lighting (15 Campuses)
- Donald ES 20 Year Life Cycle Maintenance and Repair
- Ethridge ES 20 Year Life Cycle Maintenance and Repair
- Hebron Valley ES 20 Year Life Cycle Maintenance and Repair
- Heritage ES Partial 20 Year Life Cycle Maintenance and Repair (plus casework, electrical, doors and hardware)
- Valley Ridge ES Partial 20 Year Life Cycle Maintenance and Repair
- Lakeview MS 20 Year Life Cycle Maintenance and Repair (Int. Bleachers)
- LHS Harmon Flooring
- Huffines MS Interior Bleachers
- Year 4 Track Replacements (Briarhill MS and Lamar MS)
-
Summer 2029
- Donald ES 20 Year Life Cycle Maintenance and Repair
- Ethridge ES 20 Year Life Cycle Maintenance and Repair
- Hebron Valley ES 20 Year Life Cycle Maintenance and Repair
- Heritage ES Partial 20 Year Life Cycle Maintenance and Repair (plus casework, electrical, doors and hardware)
- Valley Ridge ES Partial 20 Year Life Cycle Maintenance and Repair
- Lakeview MS 20 Year Life Cycle Maintenance and Repair (Int. Bleachers)
- Year 4 Electrical Upgrades (Parkway ES and Polser ES)
- Hebron HS 2008 Gym Rubber Flooring Replacement
- Lamar MS Gym Floor Replacement
- The Colony HS Softball Field Turf Replacement