Project Timelines
-
2023 & 2024 Bonds
Bond projects are chosen by evaluation using the Facilities Assessment document. Age is one of the main criteria, but other considerations include relevant work order history and evaluation by the facilities team. The projects are then prioritized for start and completion based on these evaluation scores.
All timelines are subject to change due to various factors such as material availability, vendor timelines, efforts to avoid campus disruption, etc.
FALL 2024
-
Marquee Replacements:
- Garden Ridge Elementary
- Old Settlers Elementary
- Lamar Middle School
- Griffin Middle School
Additions & Renovations:
- TECC-E
New Track & Field Lighting
- All five high schools
Interior Bleacher Replacements:
- Arbor Creek Middle School
Multi-Purpose Facility & Concession:
- The Colony High School
Casework Replacements (select areas):
- Arbor Creek Middle School
- Lamar Middle School
-
Emergency Responder Radio System:
- Arbor Creek MS
- Assesment Center & Textbook Warehouse
- BB Owen ES
- Briarhill MS
- Camey ES
- Castle Hills ES
- Creek Valley MS
- Degan ES
- DeLay MS
- Donald ES
- Downing MS
- Flower Mound ES
- Forest Vista ES
- Forestwood MS
- Garden Ridge ES
- Griffin MS
- Hebron Valley ES
- Heritage ES
- Hicks ES
- Highland Village ES
- Homestead ES
- Huffines MS
- Independence Elementary
- Indian Creek Elementary
-
Emergency Responder Radio System:
- Lakeland ES
- Lamar MS
- Liberty ES
- Lewisville ES
- Lewisville Learning Center
- LISD Administrative Center
- LISD Outdoor Learning Area
- Marcus HS- Softball Field
- Marcus Marauder Baseball Field
- McAuliffe ES
- McKamy MS
- Mill Street ES
- Morningside ES
- Peters Colony ES
- Polser ES
- Prarie Trail ES
- Rockbrook ES
- TECC- E
- Timber Creek ES
- Valley Ridge ES
- Vickery ES
- Wellington ES
-
*Timelines and projects are subject to change due to various factors such as materials, vendor timelines, efforts to avoid campus disruption, etc.
-
Summer 2024
Replacement or enhancement of elementary playgrounds with new accessibility style:
- Forest Vista (complete)
- Indian Creek (complete)
- Lakeland (complete)
- McAuliffe (complete)
- Morningside (complete)
- Polser (complete)
- Southridge (complete)
Marquee Replacements:
- Garden Ridge Elementary
- Old Settler Elementary
- Lamar Middle School
Furniture Replacements:
- Arbor Creek Middle School (complete)
- Briarhill Middle School (complete)
- Creekside Elementary (cafe table only) (complete)
- DeLay Middle School (complete)
- Forestwood Middle School (complete)
- Garden Ridge Elementary (complete)
- Huffines Middle School (complete)
- Independence Elementary (complete)
- Killian Middle School (complete)
- Lewisville Elementary (complete)
- Lakeland Elementary (complete)
- Lamar Middle School (complete)
- McAuliffe Elementary (complete)
- McKamy Middle School (complete)
- Morningside Elementary (complete)
- Peters Colony Elementary (complete)
Installation of elementary playground shade structures:
- Bridlewood (PreK) (complete)
- Donald (PreK) (complete)
- Ethridge (PreK) (complete)
- Forest Vista (PreK) (complete)
- Garden Ridge (Main) (complete)
- Hebron Valley (PreK) (complete)
- Heritage (PreK) (complete)
- Indian Creek (Main & PreK) (complete)
- Lakeland (Main & PreK) (complete)
- Lewisville ES (Main) (complete)
- McAuliffe (Main) (complete)
- Morningside (Main) (complete)
- Parkway (PreK) (complete)
- Polser (Main & PreK) (complete)
- Southridge (Main & PreK) (complete)
New Track & Field Lighting
- All five high schools
Flooring Replacements (select areas):
- Griffin Middle School (complete)
- Independence Elementary (complete)
- Killian Middle School (complete)
- Lakeland Elementary (complete)
- Lamar Middle School (complete)
Casework Replacements (select areas):
- Arbor Creek Middle School
- Garden Ridge Elementary (complete)
- Lamar Middle School
- Morningside Elementary (complete)
Technology:
- PK-3 Grade iPad Prep and Deployment for 24-25 SY
- 7-9, and 11-12 grade iPad Prep for 24-25 SY
- Prep Program Specific Technology for 24-25 deployment
- Update Campus Paging Systems at:
- Lewisville High School
- Rockbrook Elementary
- Independence Elementary
- McAuliffe Elementary
- Lillie Jackson Eearly Childhood Center
- UPS replacement in LISD Administrative Center Data Center
- Security Camera Storage Replacement
- Enterprise Backup System Replacement
- Enterprise Resource Planning (ERP) Software Replacement Implementation